Project Details --> Construction Progress --> Exterior    Back Next       

July 5, 2005 Cedar delivered for porch
July 5, 2005 Changed porch header
July 5, 2005 Con't vinyl trim & siding
July 3, 2005 Con't ipe decking
July 1, 2005 Con't ipe decking
July 1, 2005 Con't vinyl trim & siding
June 29, 2005 Con't vinyl trim & siding
June 28, 2005 Began ipe decking on porch
June 28, 2005 Began vinyl trim & siding
June 27, 2005 Installed exterior doors
June 27, 2005 Installed soffits
June 23, 2005 Finished installing windows
June 23, 2005 Ridge vent installed
June 22, 2005 Ridge vent delivered
June 22, 2005 Installed egress window
June 22, 2005 Started soffits
June 22, 2005 Finished roof shingles & began installing windows
June 21, 2005 Soffit delivered
June 21, 2005 Started soffit framing
June 21, 2005 Con't roofing
June 20, 2005 Windows & exterior doors delivered
June 20, 2005 Con't roofing
June 16, 2005 Wrapped house & con't roofing
June 15, 2005 Con't roofing
June 10, 2005 Finished roof felt paper

 