Status Reports
 | Monthly Status Reports
|
|
August
April
 | 06/29, Con't vinyl trim & siding |
 | 06/28, Began ipe decking |
 | 06/28, Began vinyl trim & siding |
 | 06/27, Installed exterior doors |
 | 06/27, Installed soffit |
 | 06/27, Finished sheeting low walk out end |
 | 06/23, Finished cedar header on porch |
 | 06/23, Started framing walkout end |
 | 06/23, Finished installing windows |
 | 06/23, Ridge vent installed |
 | 06/22, Ridge vent delivered |
 | 06/22, Installed egress window |
 | 06/22, Started soffits |
 | 06/22, Finished roof shingles & began
installing windows |
 | 06/22, Poured garage floor |
 | 06/22, Started cedar cover on porch
header |
 | 06/21, Cedar boards for porch delivered |
 | 06/21, Porch addition ground level
with original |
 | 06/21, Second coat on basement floor |
 | 06/21, Soffit delivered |
 | 06/21, Started soffit framing |
 | 06/21, Con't roofing |
 | 06/20, Windows & exterior doors
delivered |
 | 06/20, Framed porch header |
 | 06/20, Finished bathroom framing changes |
 | 06/20, Framed in fireplace |
 | 06/20, Con't roofing |
 | 06/17, Framed in Chimney |
 | 06/17, Finished porch joists & posts |
 | 06/17, Second grind on basement floor |
 | 06/17, Added gravel & stakes to garage
floor |
 | 06/17, Bought garage floor drain tile |
 | 06/16, Poured forms for porch addition |
 | 06/16, First grind on basement floor |
 | 06/16, Wrapped house & con't roofing |
 | 06/15, Second skim on basement floor |
 | 06/15, Con't roofing |
 | 06/15, Began to set porch joists & posts |
 | 06/15, Poured footings for porch addition |
 | 06/14, Dug trench for porch addition |
 | 06/14, Started roofing |
 | 06/13, Problem: porch roof trusses did not line up with porch
foundation. Error result of previous basement dimension error.
Solution: extend the porch foundation 8" on one end - that way the porch
foundation will be extended roof trusses 8" on all sides. |
 | 06/13, Roof Shingles delivered on roof |
 | 06/10, First skim on basement floor |
 | 06/10, Finished roof felt paper
|
 | 06/09, Filled basement floor cracks |
 | 06/09, Finished framing soffits &
sheeting |
 | 06/08, Con't framing soffits & con't
sheeting |
 | 06/07, Con't framing soffits & con't
sheeting |
 | 06/07, Cleaned basement floor & dug
out cracks |
 | 06/06, Started framing soffits & con't
sheeting |
 | 06/03, Completed 2nd retaining wall |
 | 06/03, Roof trusses were installed |
 | 06/01, Continued sheeting exterior, cut
windows & doors out, and framed garage door wall |
 | 05/28, Backfilled black dirt behind house |
 | 05/28, Set egress window well |
 | 05/28, Set one retaining wall off
walkout |
 | 05/28, Leveled porch dirt |
 | 05/28, Finished filling garage
with gravel |
 | 05/27, Continued sheeting & framing |
 | 05/26, Cut large garage door to 18" |
 | 05/26, Started sheeting exterior |
 | 05/26, Framed garage exterior walls |
 | 05/24, Finished framing exterior walls |
 | 05/24, John & Jared watered trees! |
 | 05/23, Started framing walls |
 | 05/23, Propane gas tank was delivered |
 | 05/23, Geoff, Dad & kids 'marked' trees |
 | 05/23, Geoff & Dad finished planting
trees |
 | 05/21, Filled porch with dirt |
 | 05/21, Started filling garage
with gravel |
 | 05/21, Smoothed backfill & moved
dirt |
 | 05/21, Graveled the drive |
 | 05/20, Laid out first floor |
 | 05/18, Finished laying decking |
 | 05/17, Started laying decking, we had
wanted the decking screwed on, but there was a communication break-down
with the framer |
 | 05/17, Attached ledger at ends of trusses |
 | 05/17, Built center support in basement |
 | 05/17, Finished floor trusses |
 | 05/16, Started putting on floor trusses |
 | 05/14, Geoff started stuccoing the exposed basement wall |
 | 05/13, Put sill plate on basement walls |
 | 05/13, Forms off the porch & garage
walls, small problem - large garage door was suppose to be 18' not 16'
- so we will have to cut that back. |
 | 05/11, Poured porch & garage walls |
 | 05/10, Began grinding down basement
floor, it was decided to try to grind down the floor and coat it with
the CTI System www.cti-corp.com |
 | 05/10, Porch & garage footings poured |
 | 05/07, Geoff began planting trees |
 | 05/03, Replacement roof trusses arrive |
 | 05/03, First order of framing materials arrive |
 | 04/27, Basement floor poured, the
wind picked up during the pour, and without water, it got away from them.
So, it will either have to be ripped out and redone, or smoothed. A
week or so later, cracks formed. |
 | 04/25, Floor trusses were delivered |
 | 04/25, Rough backfill done |
 | 04/25, Basement floor prep |
 | 04/19, Put black tarp over basement
walls |
 | 04/18, Hit problem, when the lumber yard came out to double
check measurements before ordering the floor trusses, it was discovered
that the basement wall dimensions were not right. The width and the length
were both over by 9". So, we had to have the house plans modified,
and re-order new roof trusses - again. Turns out the error was in
understanding the plans as they were drawn. |
 | 04/18, Finished rough-in plumbing in
basement |
 | 04/18, Finished electrical panel |
 | 04/15, Roof trusses were delivered, but the package was not
right. |
 | 04/15, Poured concrete into basement
walls |
 | 04/14, Finished laying blocks |
 | 04/13, Started laying Styrofoam blocks |
 | 04/11, Created electric panel |
 | 04/09, Finished basement tile & gravel |
 | 04/08, Dug trench for power lines |
 | 04/05, Finished pouring footings |
 | 04/04, Finished setting forms for footings |
 | 04/03, Finished gravel bed for foundation |
 | 10/11, Still working on budget, would like to start digging
hole first part of November. |
 | 10/11, We ran 1000ft of drainage tile!!
We had Hagar Backhoe run drainage tile across our property. That
should insure we don't have any water in the basement!! |
 | 10/06, Sent out change of address postcards |
 | 9/30, We moved closer into a rental home ... now instead of
3hrs away, we are 20mins. Geoff stayed behind for 4-6wks to repair
our house to sell, and transition his job |
 | 9/17, Have new bids for materials |
 | 9/04-5, We moved some dirt!!
We used an elevated scraper to create 4' slope for our walkout basement.
We also found a drainage tile on the other side of the property that we
can hook into to clear out water! |
 | 8/31, Dropped off new plans for 3 materials bids, 1
plumbing/heating/electrical bid, and 1 labor bid |
 | 8/30, Have new plans back from architect for Plan B (changes that were
found last week to reduce complexity) |
 | 8/28, Have 2 of 2 bids for electrical |
 | 8/25, Have 1 of 2 bids for masonry, we are looking at cast
stone instead of real stone (cost) |
 | 8/25, Have 1 of 2 bids for framing & finishing labor |
 | 8/25, Have 3 of 4 bids for interior painting |
 | 8/23, Looking at Plan B - alternative approach for roof &
porch, trying to cut cost - main floor and basement will remain mostly the
same, the roof would be changed to room-in-attic trusses, and the porches
would be cut back by more than half |
 | 8/21, Have 2 of 2 bids for plumbing & heating |
 | 8/20, Have 1 of 2 bids for drywall |
 | 8/16, Have 3 of 5 materials bids for SIPS panels |
 | 8/16, Possibly turning away from SIPS, we are having trouble
finding interested affordable labor - looking at traditional stick built
or factory built panels, then spraying exterior walls/roof with 3" foam |
 | 8/16, Have 1 of 2 bids for plumbing, heating, & electrical |
 | 8/10, Have 1of 4 material bids for framing lumber (interior
house, garage, windows, doors), roof (metal or asphalt), siding (cedar or
cypress, board n' batten or shakes), and soffit |
 | 8/7, Have labor/materials bid for septic system, gravel, and
crane rental |
 | 8/6, Have labor/materials bid for concrete (foundation,
walkout, basement/garage floor) |
 | 8/6, Have 2 of 5 materials bids for SIPS panels |
 | 7/28, Have 5 of 5 bids for windows |
 | 7/19, Met with architect, we now have 12 copies of our final
plans!! Now back to the budget! |
 | 7/16, Picked up near final plans |
 | 7/02, Sent in 2nd Revisions to architect |
June 2004 Status
 | 6/21, Picked up 1st revisions |
 | 6/03, Dropped on 1st revisions |
May 2004 Status
 | 5/24, Picked up initial house plans |
April 2004 Status
 | Met with architect, dropped on house plans |
 | 4/12, Drilled well |
 | 4/12, Obtained well permit |
 | 4/12, Obtained sewer permit |
 | 4/12, Temp electricity hooked up |
March 2004 Status
 | Working on house plans |
February 2004 Status
 | Working on house plans |
 | 2/02, Closed on land purchase |
|