Project Start Date: Sun 5/23/04
Project Finish Date: Tue 8/2/05
| Task ID | Task Name | Duration | Predecessors | Est Start Date | Est Finish Date | % Complete | Actual Start | Actual Finish |
|---|---|---|---|---|---|---|---|---|
| 1 | Trembley Residence At Lodemia | 146 days | Mon 2/21/05 | Tue 8/2/05 | 13% | Mon 2/21/05 | NA | |
| 2 | General Conditions | 29 days | Mon 2/21/05 | Fri 2/25/05 | 100% | Mon 2/21/05 | Fri 2/25/05 | |
| 3 | Finalize plans and develop estimate with owner, architect | 28 days | Mon 2/21/05 | Fri 2/25/05 | 100% | Mon 2/21/05 | Fri 2/25/05 | |
| 4 | Apply for Permits | 0 days | Mon 2/21/05 | Thu 2/24/05 | 100% | Mon 2/21/05 | Thu 2/24/05 | |
| 5 | Secure Septic Permit | 0 days | Mon 2/21/05 | Mon 2/21/05 | 100% | Mon 2/21/05 | Mon 2/21/05 | |
| 6 | Secure Well Permit | 0 days | 5 | Mon 2/21/05 | Mon 2/21/05 | 100% | Mon 2/21/05 | Mon 2/21/05 |
| 7 | Secure Building Permit | 0 days | Thu 2/24/05 | Thu 2/24/05 | 100% | Thu 2/24/05 | Thu 2/24/05 | |
| 8 | Site Work | 52 days | Mon 2/21/05 | Thu 5/5/05 | 53% | Mon 2/21/05 | NA | |
| 9 | Reshape Lot for Walkout | 3 days | Tue 3/1/05 | Fri 4/8/05 | 50% | Tue 3/1/05 | NA | |
| 10 | Install temporary power service | 2 days | Mon 2/21/05 | Mon 2/21/05 | 100% | Mon 2/21/05 | Mon 2/21/05 | |
| 11 | Dig Well | 5 days | Mon 2/21/05 | Fri 2/25/05 | 100% | Mon 2/21/05 | Fri 2/25/05 | |
| 12 | Install Septic System | 4 days | 26 | Fri 4/29/05 | Wed 5/4/05 | 0% | NA | NA |
| 13 | Perform Septic Inspection | 1 day | 12 | Thu 5/5/05 | Thu 5/5/05 | 0% | NA | NA |
| 14 | Foundation | 18 days | Mon 3/28/05 | Thu 4/28/05 | 37% | Mon 3/28/05 | NA | |
| 15 | Excavate for foundations | 2 days | Mon 3/28/05 | Thu 3/31/05 | 75% | Mon 3/28/05 | NA | |
| 16 | Rough In Basement Utilities | 2 days | Mon 4/18/05 | Mon 4/18/05 | 0% | NA | NA | |
| 17 | Pour Footings | 1 day | Tue 4/5/05 | Tue 4/5/05 | 100% | Tue 4/5/05 | Tue 4/5/05 | |
| 18 | Form and Pour Basement Walls | 2 days | Wed 4/13/05 | Fri 4/15/05 | 100% | Wed 4/13/05 | Fri 4/15/05 | |
| 19 | Strip basement wall forms | 1 day | 18 | Sat 4/16/05 | Sat 4/16/05 | 0% | NA | NA |
| 20 | Waterproof/insulate basement walls | 1 day | 19 | Mon 4/18/05 | Mon 4/18/05 | 0% | NA | NA |
| 21 | Excavate for Porches/Garage | 1 day | 20 | Tue 4/19/05 | Tue 4/19/05 | 0% | NA | NA |
| 22 | Pour Porch/Garage Footings | 1 day | 21 | Wed 4/20/05 | Wed 4/20/05 | 0% | NA | NA |
| 23 | Strip porch/garage Footings | 1 day | 22 | Thu 4/21/05 | Thu 4/21/05 | 0% | NA | NA |
| 24 | Pour Garage/Porch Floor | 3 days | 23 | Fri 4/22/05 | Tue 4/26/05 | 0% | NA | NA |
| 25 | Perform foundation inspection | 1 day | 15,24 | Wed 4/27/05 | Wed 4/27/05 | 0% | NA | NA |
| 26 | Backfill foundation and rough grade | 2 days | 25 | Thu 4/28/05 | Thu 4/28/05 | 0% | NA | NA |
| 27 | 24 days | 26 | Fri 4/29/05 | Fri 5/27/05 | 0% | NA | NA | |
| 28 | Frame Basement | 2 days | 26 | Fri 4/29/05 | Tue 5/3/05 | 0% | NA | NA |
| 29 | Lay Decking and Joists | 1 day | 28 | Wed 5/4/05 | Thu 5/5/05 | 0% | NA | NA |
| 30 | Frame 1st Floor Exterior | 2 days | 29 | Fri 5/6/05 | Mon 5/16/05 | 0% | NA | NA |
| 31 | Frame 1st Floor Interior | 3 days | 30 | Tue 5/17/05 | Tue 5/24/05 | 0% | NA | NA |
| 32 | Set Roof Trusses & sheathing | 2 days | 31 | Wed 5/25/05 | Thu 5/26/05 | 0% | NA | NA |
| 33 | Conduct framing inspection | 1 day | 32 | Fri 5/27/05 | Fri 5/27/05 | 0% | NA | NA |
| 34 | Dry In | 9 days | Mon 5/30/05 | Tue 6/7/05 | 0% | NA | NA | |
| 35 | Install felt, flashing and roof | 3 days | 33 | Mon 5/30/05 | Wed 6/1/05 | 0% | NA | NA |
| 36 | Hang 1st floor exterior doors | 1 day | 35 | Thu 6/2/05 | Thu 6/2/05 | 0% | NA | NA |
| 37 | Install 1st floor windows | 3 days | 36 | Fri 6/3/05 | Tue 6/7/05 | 0% | NA | NA |
| 38 | Exterior Finishes | 20 days | Wed 6/8/05 | Tue 6/14/05 | 0% | NA | NA | |
| 39 | Complete exterior siding | 5 days | 37 | Wed 6/8/05 | Tue 6/14/05 | 0% | NA | NA |
| 40 | Utility Rough-Ins and Complete Concrete | 12 days | Wed 5/25/05 | Wed 6/15/05 | 0% | NA | NA | |
| 41 | Rough-in plumbing | 5 days | 37 | Wed 6/8/05 | Tue 6/14/05 | 0% | NA | NA |
| 42 | Conduct rough-in plumbing inspection | 1 day | 41 | Wed 6/15/05 | Wed 6/15/05 | 0% | NA | NA |
| 43 | Rough-in electrical | 5 days | 31 | Wed 5/25/05 | Tue 5/31/05 | 0% | NA | NA |
| 44 | Conduct rough-in electrical inspection | 1 day | 43 | Wed 6/1/05 | Wed 6/1/05 | 0% | NA | NA |
| 45 | Rough-in HVAC | 3 days | 44 | Thu 6/2/05 | Mon 6/6/05 | 0% | NA | NA |
| 46 | Conduct rough-in HVAC inspection | 1 day | 45 | Tue 6/7/05 | Tue 6/7/05 | 0% | NA | NA |
| 47 | Rough-in communication - phone, cable, computer, alarm | 2 days | 31 | Wed 5/25/05 | Thu 5/26/05 | 0% | NA | NA |
| 48 | Interior Finishes | 30 days | Fri 5/27/05 | Thu 7/21/05 | 0% | NA | NA | |
| 49 | Drywall | 9 days | Fri 5/27/05 | Thu 6/9/05 | 0% | NA | NA | |
| 50 | Install drywall - 1st floor walls | 2 days | 47 | Fri 5/27/05 | Mon 5/30/05 | 0% | NA | NA |
| 51 | Install drywall - 1st floor overhead | 2 days | 50 | Tue 5/31/05 | Wed 6/1/05 | 0% | NA | NA |
| 52 | Install Drywall - Basement | 2 days | 51 | Thu 6/2/05 | Fri 6/3/05 | 0% | NA | NA |
| 53 | Tape and float 1st floor drywall | 1 day | 51 | Thu 6/2/05 | Tue 6/7/05 | 0% | NA | NA |
| 54 | Tape and float Basement drywall | 1 day | 52 | Mon 6/6/05 | Thu 6/9/05 | 0% | NA | NA |
| 55 | Paint and Wallpaper | 18 days | Wed 6/8/05 | Mon 6/13/05 | 0% | NA | NA | |
| 56 | Paint all except kitchen - 1st floor | 1 day | 53 | Wed 6/8/05 | Fri 6/10/05 | 0% | NA | NA |
| 57 | Hang wallpaper | 1 day | 56 | Mon 6/13/05 | Mon 6/13/05 | 0% | NA | NA |
| 58 | Cabinets | 6 days | Mon 6/27/05 | Mon 7/18/05 | 0% | NA | NA | |
| 59 | Install 1st floor - kitchen cabinets | 2 days | 79 | Mon 6/27/05 | Thu 6/30/05 | 0% | NA | NA |
| 60 | Install 1st floor - baths | 1 day | 59 | Fri 7/1/05 | Mon 7/4/05 | 0% | NA | NA |
| 61 | Install trim | 2 days | 60 | Tue 7/5/05 | Mon 7/18/05 | 0% | NA | NA |
| 62 | Finish Plumbing | 6 days | Fri 7/1/05 | Thu 7/14/05 | 0% | NA | NA | |
| 63 | Complete 1st floor - kitchen plumbing | 1 day | 59,42 | Fri 7/1/05 | Fri 7/1/05 | 0% | NA | NA |
| 64 | Complete 1st floor - bath plumbing | 2 days | 63,60 | Tue 7/5/05 | Mon 7/11/05 | 0% | NA | NA |
| 65 | Complete Basement floor - bath plumbing | 2 days | 64 | Tue 7/12/05 | Wed 7/13/05 | 0% | NA | NA |
| 66 | Conduct finish plumbing inspection | 1 day | 65 | Thu 7/14/05 | Thu 7/14/05 | 0% | NA | NA |
| 67 | Finish Electrical | 3 days | Thu 7/14/05 | Tue 7/19/05 | 0% | NA | NA | |
| 68 | Complete 1st floor circuits to service panel | 1 day | 65,44 | Thu 7/14/05 | Fri 7/15/05 | 0% | NA | NA |
| 69 | Complete Basement circuits to service panel | 1 day | 68 | Mon 7/18/05 | Mon 7/18/05 | 0% | NA | NA |
| 70 | Conduct finish electrical inspection | 1 day | 69 | Tue 7/19/05 | Tue 7/19/05 | 0% | NA | NA |
| 71 | Complete communications wiring - phone, cable, computer, alarm | 2 days | 66 | Fri 7/15/05 | Mon 7/18/05 | 0% | NA | NA |
| 72 | Finish HVAC | 3 days | Tue 7/19/05 | Thu 7/21/05 | 0% | NA | NA | |
| 73 | Complete 1st floor - zone 1 HVAC | 1 day | 71,46 | Tue 7/19/05 | Tue 7/19/05 | 0% | NA | NA |
| 74 | Complete 2nd floor - zone 2 HVAC | 1 day | 73 | Wed 7/20/05 | Wed 7/20/05 | 0% | NA | NA |
| 75 | Conduct HVAC inspection | 1 day | 74 | Thu 7/21/05 | Thu 7/21/05 | 0% | NA | NA |
| 76 | Carpet, Tile and Appliances | 8 days | Fri 6/10/05 | Tue 7/19/05 | 0% | NA | NA | |
| 77 | Install Tile/Vinyl | 3 days | 54 | Fri 6/10/05 | Tue 6/14/05 | 0% | NA | NA |
| 78 | Lay Wood Flooring 1st Floor | 2 days | 77 | Wed 6/15/05 | Fri 6/17/05 | 0% | NA | NA |
| 79 | Sand and Finish Wood Floor | 0 days? | 78 | Mon 6/20/05 | Fri 6/24/05 | 0% | NA | NA |
| 80 | Install appliances | 1 day | 61 | Tue 7/19/05 | Tue 7/19/05 | 0% | NA | NA |
| 81 | Landscaping and Grounds Work | 11 days | Fri 6/10/05 | Tue 6/14/05 | 0% | NA | NA | |
| 82 | Pour concrete driveway and sidewalks | 2 days | 54 | Fri 6/10/05 | Mon 6/13/05 | 0% | NA | NA |
| 83 | Seed and complete plantings | 2 days | 82 | Tue 6/14/05 | Tue 6/14/05 | 0% | NA | NA |
| 84 | Final Acceptance | 8 days | Fri 7/22/05 | Tue 8/2/05 | 0% | NA | NA | |
| 85 | Complete final inspection for certificate of occupancy | 1 day | 75,70,66,61 | Fri 7/22/05 | Fri 7/22/05 | 0% | NA | NA |
| 86 | Cleanup for occupancy | 1 day | 80,85 | Mon 7/25/05 | Mon 7/25/05 | 0% | NA | NA |
| 87 | Perform final walk-through inspection | 1 day | 86 | Tue 7/26/05 | Tue 7/26/05 | 0% | NA | NA |
| 88 | Complete punch list items | 5 days | 87 | Wed 7/27/05 | Tue 8/2/05 | 0% | NA | NA |