Residential Construction


Project Start Date: Sun 5/23/04
Project Finish Date: Tue 8/2/05

Project Tasks

Task ID
Task Name
DurationPredecessorsEst Start DateEst Finish Date% CompleteActual StartActual Finish
1
Trembley Residence At Lodemia
146 days Mon 2/21/05Tue 8/2/0513%Mon 2/21/05NA
2
General Conditions
29 days Mon 2/21/05Fri 2/25/05100%Mon 2/21/05Fri 2/25/05
3
Finalize plans and develop estimate with owner, architect
28 days Mon 2/21/05Fri 2/25/05100%Mon 2/21/05Fri 2/25/05
4
Apply for Permits
0 days Mon 2/21/05Thu 2/24/05100%Mon 2/21/05Thu 2/24/05
5
Secure Septic Permit
0 days Mon 2/21/05Mon 2/21/05100%Mon 2/21/05Mon 2/21/05
6
Secure Well Permit
0 days5Mon 2/21/05Mon 2/21/05100%Mon 2/21/05Mon 2/21/05
7
Secure Building Permit
0 days Thu 2/24/05Thu 2/24/05100%Thu 2/24/05Thu 2/24/05
8
Site Work
52 days Mon 2/21/05Thu 5/5/0553%Mon 2/21/05NA
9
Reshape Lot for Walkout
3 days Tue 3/1/05Fri 4/8/0550%Tue 3/1/05NA
10
Install temporary power service
2 days Mon 2/21/05Mon 2/21/05100%Mon 2/21/05Mon 2/21/05
11
Dig Well
5 days Mon 2/21/05Fri 2/25/05100%Mon 2/21/05Fri 2/25/05
12
Install Septic System
4 days26Fri 4/29/05Wed 5/4/050%NANA
13
Perform Septic Inspection
1 day12Thu 5/5/05Thu 5/5/050%NANA
14
Foundation
18 days Mon 3/28/05Thu 4/28/0537%Mon 3/28/05NA
15
Excavate for foundations
2 days Mon 3/28/05Thu 3/31/0575%Mon 3/28/05NA
16
Rough In Basement Utilities
2 days Mon 4/18/05Mon 4/18/050%NANA
17
Pour Footings
1 day Tue 4/5/05Tue 4/5/05100%Tue 4/5/05Tue 4/5/05
18
Form and Pour Basement Walls
2 days Wed 4/13/05Fri 4/15/05100%Wed 4/13/05Fri 4/15/05
19
Strip basement wall forms
1 day18Sat 4/16/05Sat 4/16/050%NANA
20
Waterproof/insulate basement walls
1 day19Mon 4/18/05Mon 4/18/050%NANA
21
Excavate for Porches/Garage
1 day20Tue 4/19/05Tue 4/19/050%NANA
22
Pour Porch/Garage Footings
1 day21Wed 4/20/05Wed 4/20/050%NANA
23
Strip porch/garage Footings
1 day22Thu 4/21/05Thu 4/21/050%NANA
24
Pour Garage/Porch Floor
3 days23Fri 4/22/05Tue 4/26/050%NANA
25
Perform foundation inspection
1 day15,24Wed 4/27/05Wed 4/27/050%NANA
26
Backfill foundation and rough grade
2 days25Thu 4/28/05Thu 4/28/050%NANA
27 24 days26Fri 4/29/05Fri 5/27/050%NANA
28
Frame Basement
2 days26Fri 4/29/05Tue 5/3/050%NANA
29
Lay Decking and Joists
1 day28Wed 5/4/05Thu 5/5/050%NANA
30
Frame 1st Floor Exterior
2 days29Fri 5/6/05Mon 5/16/050%NANA
31
Frame 1st Floor Interior
3 days30Tue 5/17/05Tue 5/24/050%NANA
32
Set Roof Trusses & sheathing
2 days31Wed 5/25/05Thu 5/26/050%NANA
33
Conduct framing inspection
1 day32Fri 5/27/05Fri 5/27/050%NANA
34
Dry In
9 days Mon 5/30/05Tue 6/7/050%NANA
35
Install felt, flashing and roof
3 days33Mon 5/30/05Wed 6/1/050%NANA
36
Hang 1st floor exterior doors
1 day35Thu 6/2/05Thu 6/2/050%NANA
37
Install 1st floor windows
3 days36Fri 6/3/05Tue 6/7/050%NANA
38
Exterior Finishes
20 days Wed 6/8/05Tue 6/14/050%NANA
39
Complete exterior siding
5 days37Wed 6/8/05Tue 6/14/050%NANA
40
Utility Rough-Ins and Complete Concrete
12 days Wed 5/25/05Wed 6/15/050%NANA
41
Rough-in plumbing
5 days37Wed 6/8/05Tue 6/14/050%NANA
42
Conduct rough-in plumbing inspection
1 day41Wed 6/15/05Wed 6/15/050%NANA
43
Rough-in electrical
5 days31Wed 5/25/05Tue 5/31/050%NANA
44
Conduct rough-in electrical inspection
1 day43Wed 6/1/05Wed 6/1/050%NANA
45
Rough-in HVAC
3 days44Thu 6/2/05Mon 6/6/050%NANA
46
Conduct rough-in HVAC inspection
1 day45Tue 6/7/05Tue 6/7/050%NANA
47
Rough-in communication - phone, cable, computer, alarm
2 days31Wed 5/25/05Thu 5/26/050%NANA
48
Interior Finishes
30 days Fri 5/27/05Thu 7/21/050%NANA
49
Drywall
9 days Fri 5/27/05Thu 6/9/050%NANA
50
Install drywall - 1st floor walls
2 days47Fri 5/27/05Mon 5/30/050%NANA
51
Install drywall - 1st floor overhead
2 days50Tue 5/31/05Wed 6/1/050%NANA
52
Install Drywall - Basement
2 days51Thu 6/2/05Fri 6/3/050%NANA
53
Tape and float 1st floor drywall
1 day51Thu 6/2/05Tue 6/7/050%NANA
54
Tape and float Basement drywall
1 day52Mon 6/6/05Thu 6/9/050%NANA
55
Paint and Wallpaper
18 days Wed 6/8/05Mon 6/13/050%NANA
56
Paint all except kitchen - 1st floor
1 day53Wed 6/8/05Fri 6/10/050%NANA
57
Hang wallpaper
1 day56Mon 6/13/05Mon 6/13/050%NANA
58
Cabinets
6 days Mon 6/27/05Mon 7/18/050%NANA
59
Install 1st floor - kitchen cabinets
2 days79Mon 6/27/05Thu 6/30/050%NANA
60
Install 1st floor - baths
1 day59Fri 7/1/05Mon 7/4/050%NANA
61
Install trim
2 days60Tue 7/5/05Mon 7/18/050%NANA
62
Finish Plumbing
6 days Fri 7/1/05Thu 7/14/050%NANA
63
Complete 1st floor - kitchen plumbing
1 day59,42Fri 7/1/05Fri 7/1/050%NANA
64
Complete 1st floor - bath plumbing
2 days63,60Tue 7/5/05Mon 7/11/050%NANA
65
Complete Basement floor - bath plumbing
2 days64Tue 7/12/05Wed 7/13/050%NANA
66
Conduct finish plumbing inspection
1 day65Thu 7/14/05Thu 7/14/050%NANA
67
Finish Electrical
3 days Thu 7/14/05Tue 7/19/050%NANA
68
Complete 1st floor circuits to service panel
1 day65,44Thu 7/14/05Fri 7/15/050%NANA
69
Complete Basement circuits to service panel
1 day68Mon 7/18/05Mon 7/18/050%NANA
70
Conduct finish electrical inspection
1 day69Tue 7/19/05Tue 7/19/050%NANA
71
Complete communications wiring - phone, cable, computer, alarm
2 days66Fri 7/15/05Mon 7/18/050%NANA
72
Finish HVAC
3 days Tue 7/19/05Thu 7/21/050%NANA
73
Complete 1st floor - zone 1 HVAC
1 day71,46Tue 7/19/05Tue 7/19/050%NANA
74
Complete 2nd floor - zone 2 HVAC
1 day73Wed 7/20/05Wed 7/20/050%NANA
75
Conduct HVAC inspection
1 day74Thu 7/21/05Thu 7/21/050%NANA
76
Carpet, Tile and Appliances
8 days Fri 6/10/05Tue 7/19/050%NANA
77
Install Tile/Vinyl
3 days54Fri 6/10/05Tue 6/14/050%NANA
78
Lay Wood Flooring 1st Floor
2 days77Wed 6/15/05Fri 6/17/050%NANA
79
Sand and Finish Wood Floor
0 days?78Mon 6/20/05Fri 6/24/050%NANA
80
Install appliances
1 day61Tue 7/19/05Tue 7/19/050%NANA
81
Landscaping and Grounds Work
11 days Fri 6/10/05Tue 6/14/050%NANA
82
Pour concrete driveway and sidewalks
2 days54Fri 6/10/05Mon 6/13/050%NANA
83
Seed and complete plantings
2 days82Tue 6/14/05Tue 6/14/050%NANA
84
Final Acceptance
8 days Fri 7/22/05Tue 8/2/050%NANA
85
Complete final inspection for certificate of occupancy
1 day75,70,66,61Fri 7/22/05Fri 7/22/050%NANA
86
Cleanup for occupancy
1 day80,85Mon 7/25/05Mon 7/25/050%NANA
87
Perform final walk-through inspection
1 day86Tue 7/26/05Tue 7/26/050%NANA
88
Complete punch list items
5 days87Wed 7/27/05Tue 8/2/050%NANA